You must know these abbreviations for the PMP Exam:

Question Answer
What is "EV"?Earned Value
What is "AC"?Actual Cost
What is "CV"?Cost Variance
What is "CPI"?Cost Performance Index
What is "SV"?Schedule Variance
What is "SPI"?Schedule Performance Index
What is "ETC"?Estimate to Complete
What is "EAC"?Estimate at Completion
What is "VAC"?Variance at Completion
What is "AC"?Actual Cost
What is "BAC"?Budget at Completion
memorize

You must know the following basic EV formulas for the PMP Exam:

Question Answer
EV =% x BAC
PV =% x BAC
CV =EV - AC
SV =EV - PV
CPI =EV / AC
SPI =EV / PV
ETC =EAC-AC
(std method) TCPI =(BAC-EV) / (BAC-AC)
(alt) TCPI =(BAC-EV) / (EAC-AC)
VAC =BAC - EAC
EAC (typ) =BAC / CPI
EAC (atyp) =AC + (BAC - EV)
EAC (bot_up) =AC + (BAC - EV) / (CPI x SPI)
memorize

You must know how to use the following communications channel formula for the PMP Exam:

Question Answer
CC =n * (n-1) / 2
memorize