This Page is designed to help memorize Table 3-1 from the PMBOK Guide 5th Edition Page 61

Process Groups ( Table Headers In order Left to Right ) Note : all end with "Process Group"

 

Question Answer
Group Column 1Initiating
Group Column 2Planning
Group Column 3Executing
Group Column 4Monitoring and Controlling
Group Column 5Closing
memorize

Knowledge Areas ( Row Headers in order Top to Bottom ) Note : all begin "Project" and end with "Management"

 

Question Answer
Row 1Integration
Row 2Scope
Row 3Time
Row 4Cost
Row 5Quality
Row 6Human Resources
Row 7Communications
Row 8Risk
Row 9Procurement
Row 10Stakeholder
memorize

# of Processes in each Process Group

 

Question Answer
Initiating2
Planning24
Executing8
Monitoring and Controlling11
Closing2
memorize

# Processes in each Knowledge Group:

 

Question Answer
Integration6
Scope6
Time7
Cost4
Quality3
Human Resource4
Communications3
Risk6
Procurement4
Stakeholder4
memorize

Processes in Knowledge Area "4.0 Project Integration Management"

 

Question Answer
Initiating 1Develop Project Charter
Planning 1Develop Project Management Plan
Executing 1Direct and Manage Project Work
Monitoring & Controlling 1Monitor and Control Project Work
Monitoring & Controlling 2Perform Integrated Change Control
Closing 1Close Project or Phase
memorize

Processes in Knowledge Area "5.0 Project Scope Management"

 

Question Answer
Planning 1Plan Scope Management
Planning 2Collect Requirements
Planning 3Define Scope
Planning 4Create WBS
Monitoring and Controlling 1Validate Scope
Monitoring and Controlling 2Control Scope
memorize

Processes in Knowledge Area "6.0 Project Time Management"

 

Question Answer
Planning 1Plan Schedule Management
Planning 2Define Activities
Planning 3Sequence Activities
Planning 4Estimate Activity Resources
Planning 5Estimate Activity Durations
Planning 6Develop Schedule
Monitoring & Controlling 1Control Schedule
memorize

Processes in Knowledge Area "7.0 Project Cost Management"

 

Question Answer
Planning 1Plan Cost Management
Planning 2Estimate Costs
Planning 3Determine Budget
Monitor & Controlling 1Control Costs
memorize

Processes in Knowledge Area "8.0 Project Quality Management"

 

Question Answer
Planning 1Plan Quality Management
Executing 1Perform Quality Assurance
Monitoring and Controlling 1Control Quality
memorize

Processes in Knowledge Area "9.0 Project Human Resource Management"

 

Question Answer
Planning 1Plan Human Resource Management
Executing 1Acquire Project Team
Executing 2Develop Project Team
Executing 3Manage Project Team
memorize

Processes in Knowledge Area "10.0 Project Communications Management"

 

Question Answer
Planning 1Plan Communications Management
Executing 1Manage Communications
Monitoring & Controlling 1Control Communications
memorize

Processes in Knowledge Area "11.0 Project Risk Management"

 

Question Answer
Planning 1Plan Risk Management
Planning 2Identify Risks
Planning 3Perform Qualitative Risk Analysis
Planning 4Perform Quantitative Risk Analysis
Planning 5Plan Risk Responses
Monitor & Controlling 1Control Risks
memorize

Processes in Knowledge Area "12.0 Project Procurement Management"

 

Question Answer
Planning 1Plan Procurement Management
Executing 1Conduct Procurements
Monitor and Controlling 1Control Procurements
Closing 1Close Procurements
memorize

Processes in Knowledge Area "13.0 Project Stakeholder Management"

 

Question Answer
Initiating 1Identify Stakeholders
Planning 1Plan Stakeholder Management
Executing 1Manage Stakeholder Engagement
Monitoring & Controlling 1Control Stakeholder Engagement
memorize

Processes in Process Group "Initiating Process Group"

 

Question Answer
Integration 1Develop Project Charter
Stakeholder 1Identify Stakeholders
memorize

Processes in Process Group "Planning Process Group"

 

Question Answer
Integration 1Develop Project Management Plan
Scope 1Plan Scope Management
Scope 2Collect Requirements
Scope 3Define Scope
Scope 4Create WBS
Time 1Plan Schedule Management
Time 2Define Activities
Time 3Sequence Activities
Time 4Estimate Activity Resources
Time 5Estimate Activity Durations
Time 6Develop Schedule
Cost 1Plan Cost Management
Cost 2Estimate Costs
Cost 3Determine Budget
Quality 1Plan Quality Management
Human Resource 1Plan Human Resources Management
Communications 1Plan Communications Management
Risk 1Plan Risk Management
Risk 2Identify Risks
Risk 3Perform Qualitative Risk Analysis
Risk 4Perform Quantitative Risk Analysis
Risk 5Plan Risk Responses
Procurement 1Plan Procurement Management
Stakeholder 1Plan Stakeholder Management
memorize

Processes in Process Group "Executing Process Group"

 

Question Answer
Integration 1Direct and Manage Project Work
Quality 1Perform Quality Assurance
Human Resource 1Acquire Project Team
Human Resource 2Develop Project Team
Human Resource 3Manage Project Team
Communications 1Manage Communications
Procurement 1Conduct Procurements
Stakeholder 1Manage Stakeholder Engagement
memorize

Processes in Process Group " Monitor & Controlling Process Group"

 

Question Answer
Integration 1Monitor and Control Project Work
Integration 2Perform Integrated Change Control
Scope 1Validate Scope
Scope 2Control Scope
Time 1Control Schedule
Cost 1Control Costs
Quality 1Control Quality
Communications 1Control Communications
Risk 1Control Risks
Procurement 1Control Procurements
Stakeholder 1Control Stakeholder Engagement
memorize

Processes in Process Group "Closing Process Group"

 

Question Answer
Integration 1Close Project or Phase
Procurement 1Close Procurements