PMBOK Table 3-1 5th Edition

rename
fryer's version from 2016-02-17 20:45

Process Groups (Table Headers) Note : all End with "Process Group"

Question Answer
Group Column 1Initiating
Group Column 2Planning
Group Column 3Executing
Group Column 4Monitoring and Controlling
Group Column 5Closing
memorize

Knowledge Areas (Row Headers in order top to bottom) Note : all begin "Project" and end with "Management"

Question Answer
Row 1Integration
Row 2Scope
Row 3Time
Row 4Cost
Row 5Quality
Row 6Human Resource
Row 7Communications
Row 8Risk
Row 9Procurement
Row 10Stakeholder
memorize

# of Processes in each Process Group

Question Answer
Initiating2
Planning24
Executing8
Monitoring and Controlling11
Closing2
memorize

# Processes in each Knowledge Area:

Question Answer
Integration6
Scope6
Time7
Cost4
Quality3
Human Resource4
Communications3
Risk6
Procurement4
Stakeholder4
memorize

Processes in Knowledge Area "Project Integration Management"

Question Answer
InitiatingDevelop Project Charter
PlanningDevelop Project Management Plan
ExecutingDirect and Manage Project Work
Monitoring and Controlling 1Monitor and Control Project Work
Monitoring and Controlling 2Perform Integrated Change Control
ClosingClose Project or Phase
memorize

Processes in Knowledge Area "Project Scope Management"

Question Answer
Planning 1Plan Scope Management
Planning 2Collect Requirements
Planning 3Define Scope
Planning 4Create WBS
Monitoring and Controlling 1Validate Scope
Monitoring and Controlling 2Control Scope
memorize

Processes in Knowledge Area "Project Project Time Management"

Question Answer
Planning 1Plan Schedule Management
Planning 2Define Activities
Planning 3Sequence Activities
Planning 4Estimate Activity Resources
Planning 5Estimate Activity Durations
Planning 6Develop Schedule
Monitoring and ControllingControl Schedule
memorize

Processes in Knowledge Area "Project Project Cost Management"

Question Answer
Planning 1Plan Cost Management
Planning 2Estimate Costs
Planning 3Determine Budget
Monitoring and ControllingControl Costs
memorize

Processes in Knowledge Area "Project Quality Management"

Question Answer
Planning 1Plan Quality Management
Executing 1Perform Quality Assurance
Monitoring and ControllingControl Quality
memorize

Processes in Knowledge Area "Project Human Resource Management"

Question Answer
PlanningPlan Human Resource Management
Executing 1Acquire Project Team
Executing 2Develop Project Team
Executing 3Manage Project Team
memorize

Processes in Knowledge Area "Project Communications Management"

Question Answer
PlanningPlan Communications Management
ExecutingManage Communications
Monitoring and ControllingControl Communications
memorize

Processes in Knowledge Area "Project Risk Management"

Question Answer
Planning 1Plan Risk Management
Planning 2Identify Risks
Planning 3Perform Qualitative Risk Analysis
Planning 4Perform Quantitiative Risk Analysis
Planning 5Plan Risk Responses
Monitoring and Controlling 1Control Risks
memorize

Processes in Knowledge Area "Project Procurement Management"

Question Answer
PlanningPlan Procurement Management
ExecutingConduct Procurements
Monitoring and ControllingControl Procurements
ClosingClose Procurements
memorize

Processes in Knowledge Area "Project Stakeholder Management"

Question Answer
InitiatingIdentify Stakeholders
PlanningPlan Stakeholder Management
ExecutingManage Stakeholder Engagement
Monitoring and ControllingControl Stakeholder Engagement
memorize

Processes in Process Group "Initiating Process Group"

Question Answer
Integration4.1 Develop Project Charter
Stakeholder13.1 Identify Stakeholders
memorize

Processes in Process Group "Planning Process Group"

Question Answer
Integration4.2 Develop Project Management Plan
Scope 15.1 Plan Scope Management
Scope 25.2 Collect Requirements
Scope 35.3 Define Scope
Scope 45.4 Create WBS
Time 16.1 Plan Schedule Management
Time 26.2 Define Activities
Time 36.3 Sequence Activities
Time 46.4 Estimate Activity Resources
Time 56.5 Estimate Activity Durations
Time 66.6 Develop Schedule
Cost 17.1 Plan Cost Management
Cost 27.2 Estimate Costs
Cost 37.3 Determine Budget
Quality 18.1 Plan Quality Management
Human Resource9.1 Plan Human Resource Management
Communications10.1 Plan Communcations Management
Risk 111.1 Plan Risk Management
Risk 211.2 Identify Risks
Risk 3 11.3 Perform Qualitative Risk Analysis
Risk 411.4 Perform Quantitative Risk Analysis
Risk 511.5 Plan Risk Responses
Procurement12.1 Plan Procurement Management
Stakeholder13.2 Plan Stakeholder Management
memorize

Processes in Process Group "Executing Process Group"

Question Answer
Integration4.3 Direct and Manage Project Work
Quality8.2 Perform Quality Assurance
Human Resource 19.2 Acquire Project Team
Human Resource 29.3 Develop Project Team
Human Resource 39.4 Manage Project Team
Communications10.2 Manage Communications
Procurement12.2 Conduct Procurements
Stakeholder13.3 Manage Stakeholder Engagement
memorize

Processes in Process Group "Monitoring and Controlling Process Group"

Question Answer
Integration 14.4 Monitor and Control Project Work
Integration 24.5 Perform Integrated Change Control
Scope 15.5 Validate Scope
Scope 25.6 Control Scope
Time6.7 Control Schedule
Cost7.4 Control Costs
Quality8.3 Control Quality
Communications10.3 Control Communications
Risk11.6 Control Risks
Procurement12.3 Control Procurements
Stakeholder13.4 Control Stakeholder Engagement
memorize

Processes in Process Group "Closing Process Group"

Question Answer
Integration4.6 Close Project or Phase
Procurement12.4 Close Procurements