Earned Value Summery

rename
riyupome's version from 2015-12-07 23:49

Section 1

Question Answer
SVSchedule Variance
EVEarned Value
ACActual Cost
PVPlanned Value
CVCost Variance
BACBugdet At Completion
VACVariance At Completion
CPICost Performance Index
SPISchedule Performance Index
EACEstimate At Completion
ETCEstimate To Complete
TCPITo Complete Performance Index
memorize

Section 2

Question Answer
SVSV = EV - PV
CVCV = EV - AC
EV Sum of the planned value of all completed work
Pass
CPICPI = EV / AC
SPISPI = EV / PV
Pass
Pass